Scheduled maintenance for Trellix ePO - SaaS: EU-Central (EU001)
Scheduled Maintenance Report for Trellix
Completed
The scheduled maintenance has been completed.
Posted Dec 03, 2023 - 20:43 UTC
Update
Scheduled maintenance is still in progress. We will provide updates as necessary.
Posted Dec 03, 2023 - 16:38 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Dec 03, 2023 - 15:15 UTC
Scheduled
During this maintenance, event processing for the following services will be delayed:
- ePO SaaS Events (Threat Events, DLP Incidents, DLP Web Proxy, FRP)
- ePO SaaS Automatic responses
- FRP new removal media initialization and recovery key requests

These services will not be available:
- APIs
- TIE reputation change

During this maintenance, managed endpoints will continue to be protected and the ePO - SaaS console will be accessible.
Posted Dec 03, 2023 - 15:12 UTC
This scheduled maintenance affected: Trellix ePO - SaaS: EU-Central (EU001) (Endpoint Communication).